Man assembling a white table with brown legs. The man is wearing a blue jumpsuit and leaning over the furniture.
Man assembling a white table with brown legs. The man is wearing a blue jumpsuit and leaning over the furniture.
Man assembling a white table with brown legs. The man is wearing a blue jumpsuit and leaning over the furniture.
Man assembling a white table with brown legs. The man is wearing a blue jumpsuit and leaning over the furniture.
Man assembling a white table with brown legs. The man is wearing a blue jumpsuit and leaning over the furniture.
Man assembling a white table with brown legs. The man is wearing a blue jumpsuit and leaning over the furniture.

Complete Projects
6 Weeks Earlier

Complete Projects
6 Weeks Earlier

Revolutionary tool-free assembly transforms your critical path. 10x faster manufacturing speed, 3x faster installation. 8x fewer deliveries. 75% carbon reduction for ESG compliance. Zero installation delays.

See Real Project Impact

See Real Project Impact

See Real Project Impact

See Real Project Impact

See Real Project Impact

See Real Project Impact

0

0

20%

20%

0%

0%

0%

0%

Weeks Earlier Completion

£180k

£180k

20%

20%

180%

180%

20%

20%

Savings per 200 Units

24%

24%

20%

20%

20%

20%

Fewer Callbacks

Project Manager's Life

From morning crisis to afternoon success - see the Innoclic transformation

8:00 AM - Traditional Method

Email: "We Have a Problem"

Contractor reports wrong kitchen units delivered to Phase 3. 8 HGVs blocking site entrance. Residents complaining. Storage warehouse at capacity. Rain forecast will damage MDF. Installation team idle, burning £2,400/day.

3 Week Delay Imminent

8:00 AM - With Innoclic

Email: "Ahead of Schedule"

Phase 3 Innoclic units arrived in single van yesterday. Stored in corridors, ready for installation. Team starting Block C at 9am. Weather irrelevant - all indoors. Expecting 20 units complete today.

3 Days Ahead of Schedule

8:00 AM - Traditional Method

Email: "We Have a Problem"

Contractor reports wrong kitchen units delivered to Phase 3. 8 HGVs blocking site entrance. Residents complaining. Storage warehouse at capacity. Rain forecast will damage MDF. Installation team idle, burning £2,400/day.

3 Week Delay Imminent

8:00 AM - With Innoclic

Email: "Ahead of Schedule"

Phase 3 Innoclic units arrived in single van yesterday. Stored in corridors, ready for installation. Team starting Block C at 9am. Weather irrelevant - all indoors. Expecting 20 units complete today.

3 Days Ahead of Schedule

8:00 AM - Traditional Method

Email: "We Have a Problem"

Contractor reports wrong kitchen units delivered to Phase 3. 8 HGVs blocking site entrance. Residents complaining. Storage warehouse at capacity. Rain forecast will damage MDF. Installation team idle, burning £2,400/day.

3 Week Delay Imminent

8:00 AM - With Innoclic

Email: "Ahead of Schedule"

Phase 3 Innoclic units arrived in single van yesterday. Stored in corridors, ready for installation. Team starting Block C at 9am. Weather irrelevant - all indoors. Expecting 20 units complete today.

3 Days Ahead of Schedule

10:00 AM - Traditional Method

Crisis Meeting

Emergency meeting with QS and contractors. Discussing air freight for correct units (£45k extra). Storage solutions needed urgently. Client demanding update. Penalty clauses looming at £5k/day from next week.

Budget Overrun £120k

10:00 AM - With Innoclic

Smooth Operations

First 5 apartments already complete. Perfect alignment every time. No tools needed, no errors possible. Client visiting at 2pm for inspection. Team confident of completing 20 units today.

£1,400/unit Savings

10:00 AM - Traditional Method

Crisis Meeting

Emergency meeting with QS and contractors. Discussing air freight for correct units (£45k extra). Storage solutions needed urgently. Client demanding update. Penalty clauses looming at £5k/day from next week.

Budget Overrun £120k

10:00 AM - With Innoclic

Smooth Operations

First 5 apartments already complete. Perfect alignment every time. No tools needed, no errors possible. Client visiting at 2pm for inspection. Team confident of completing 20 units today.

£1,400/unit Savings

10:00 AM - Traditional Method

Crisis Meeting

Emergency meeting with QS and contractors. Discussing air freight for correct units (£45k extra). Storage solutions needed urgently. Client demanding update. Penalty clauses looming at £5k/day from next week.

Budget Overrun £120k

10:00 AM - With Innoclic

Smooth Operations

First 5 apartments already complete. Perfect alignment every time. No tools needed, no errors possible. Client visiting at 2pm for inspection. Team confident of completing 20 units today.

£1,400/unit Savings

12:00 PM - Traditional Method

Damage Control

Negotiating with other trades to reschedule. Electrical and plumbing now delayed. Entire programme slipping. Marketing team informed show apartments won't be ready. Sales launch postponed.

Cascade Effect on All Trades

12:00 PM - With Innoclic

Timeline Recovered

10 apartments complete before lunch. Other trades can follow immediately - no waiting. Show apartments ready 2 weeks early. Marketing team preparing early launch campaign.

Revenue Generation Accelerated

12:00 PM - Traditional Method

Damage Control

Negotiating with other trades to reschedule. Electrical and plumbing now delayed. Entire programme slipping. Marketing team informed show apartments won't be ready. Sales launch postponed.

Cascade Effect on All Trades

12:00 PM - With Innoclic

Timeline Recovered

10 apartments complete before lunch. Other trades can follow immediately - no waiting. Show apartments ready 2 weeks early. Marketing team preparing early launch campaign.

Revenue Generation Accelerated

12:00 PM - Traditional Method

Damage Control

Negotiating with other trades to reschedule. Electrical and plumbing now delayed. Entire programme slipping. Marketing team informed show apartments won't be ready. Sales launch postponed.

Cascade Effect on All Trades

12:00 PM - With Innoclic

Timeline Recovered

10 apartments complete before lunch. Other trades can follow immediately - no waiting. Show apartments ready 2 weeks early. Marketing team preparing early launch campaign.

Revenue Generation Accelerated

5:00 PM - Traditional Method

Damage Report

2 kitchens partially installed with multiple errors. Weekend overtime approved at 2x rates. Board report: "Significant delays, exploring mitigation options." Resident compensation claims starting

Project Red Status

5:00 PM - With Innoclic

Victory Report

20 apartments fully complete, zero defects. Client delighted at inspection - considering Innoclic for Phase 4. Board report: "6 weeks ahead, £280k under budget." First residents moving in next week.

Project Green Status

5:00 PM - Traditional Method

Damage Report

2 kitchens partially installed with multiple errors. Weekend overtime approved at 2x rates. Board report: "Significant delays, exploring mitigation options." Resident compensation claims starting

Project Red Status

5:00 PM - With Innoclic

Victory Report

20 apartments fully complete, zero defects. Client delighted at inspection - considering Innoclic for Phase 4. Board report: "6 weeks ahead, £280k under budget." First residents moving in next week.

Project Green Status

5:00 PM - Traditional Method

Damage Report

2 kitchens partially installed with multiple errors. Weekend overtime approved at 2x rates. Board report: "Significant delays, exploring mitigation options." Resident compensation claims starting

Project Red Status

5:00 PM - With Innoclic

Victory Report

20 apartments fully complete, zero defects. Client delighted at inspection - considering Innoclic for Phase 4. Board report: "6 weeks ahead, £280k under budget." First residents moving in next week.

Project Green Status

Project Challenge

Traditional Method

Innoclic Solution

Programme Duration

Programme Duration

Programme Duration

Programme Duration

8-12 hours per kitchen

8-12 hours per kitchen

8-12 hours per kitchen

8-12 hours per kitchen

45 minutes per kitchen

45 minutes per kitchen

45 minutes per kitchen

45 minutes per kitchen

HGV Movements

HGV Movements

HGV Movements

HGV Movements

8 trucks per 10 apartments

8 trucks per 10 apartments

8 trucks per 10 apartments

8 trucks per 10 apartments

1 van per 20 apartments

1 van per 20 apartments

1 van per 20 apartments

1 van per 20 apartments

Storage Required

Storage Required

Storage Required

Storage Required

External warehouse (£15k/month)

External warehouse (£15k/month)

External warehouse (£15k/month)

External warehouse (£15k/month)

Corridor storage only

Corridor storage only

Corridor storage only

Corridor storage only

Installation Errors

Installation Errors

Installation Errors

Installation Errors

18% callback rate

18% callback rate

18% callback rate

18% callback rate

<1% callback rate

<1% callback rate

<1% callback rate

<1% callback rate

Weather Delays

Weather Delays

Weather Delays

Weather Delays

Average 12 days per project

Average 12 days per project

Average 12 days per project

Average 12 days per project

Zero weather impact

Zero weather impact

Zero weather impact

Zero weather impact

Labor Cost

Labor Cost

Labor Cost

Labor Cost

£800-1200 per unit

£800-1200 per unit

£800-1200 per unit

£800-1200 per unit

£150-200 per unit

£150-200 per unit

£150-200 per unit

£150-200 per unit

Critical Path Impact

Critical Path Impact

Critical Path Impact

Critical Path Impact

Major bottleneck

Major bottleneck

Major bottleneck

Major bottleneck

Parallel workflow enabled

Parallel workflow enabled

Parallel workflow enabled

Parallel workflow enabled

Carbon Footprint

Carbon Footprint

Carbon Footprint

Carbon Footprint

Standard emissions

Standard emissions

Standard emissions

Standard emissions

75% reduction

75% reduction

75% reduction

75% reduction

BREEAM Points

BREEAM Points

BREEAM Points

BREEAM Points

0-2 points

0-2 points

0-2 points

0-2 points

12+ points available

12+ points available

12+ points available

12+ points available

Site Safety

Site Safety

Site Safety

Site Safety

Power tools, manual handling risks

Power tools, manual handling risks

Power tools, manual handling risks

Power tools, manual handling risks

Zero tools, reduced injuries

Zero tools, reduced injuries

Zero tools, reduced injuries

Zero tools, reduced injuries

UK Construction Industry Reality

UK Installation
Industry Reality

Industry-wide challenges demand revolutionary solutions

5%

5%

Projects Over Budget

RICS Survey 2024

5%

5%

Projects Over Budget

RICS Survey 2024

5%

5%

Projects Over Budget

RICS Survey 2024

5%

5%

Projects Over Budget

RICS Survey 2024

$0bn

$0bn

Annual Delay Costs

Construction Leadership Council

$0bn

$0bn

Annual Delay Costs

Construction Leadership Council

$0bn

$0bn

Annual Delay Costs

Construction Leadership Council

$0bn

$0bn

Annual Delay Costs

Construction Leadership Council

217,000

Worker Shortage

CITB Report 2024

15%

15%

ESG Non-Compliance Risk

UK Green Building Council

15%

15%

ESG Non-Compliance Risk

UK Green Building Council

15%

15%

ESG Non-Compliance Risk

UK Green Building Council

15%

15%

ESG Non-Compliance Risk

UK Green Building Council

Regulation Pressure

Future Homes Standard 2026 requires 75% carbon reduction. Building Safety Act increasing compliance burden. ESG reporting mandatory for large developers.

Regulation Pressure

Future Homes Standard 2026 requires 75% carbon reduction. Building Safety Act increasing compliance burden. ESG reporting mandatory for large developers.

Regulation Pressure

Future Homes Standard 2026 requires 75% carbon reduction. Building Safety Act increasing compliance burden. ESG reporting mandatory for large developers.

Regulation Pressure

Future Homes Standard 2026 requires 75% carbon reduction. Building Safety Act increasing compliance burden. ESG reporting mandatory for large developers.

Market Competition

BTR sector growing 25% annually requiring faster delivery. International competition with modular systems. Resident expectations for quality rising.

Market Competition

BTR sector growing 25% annually requiring faster delivery. International competition with modular systems. Resident expectations for quality rising.

Market Competition

BTR sector growing 25% annually requiring faster delivery. International competition with modular systems. Resident expectations for quality rising.

Market Competition

BTR sector growing 25% annually requiring faster delivery. International competition with modular systems. Resident expectations for quality rising.

Innoclic Solution

Exceeds all regulatory requirements. 6 weeks faster than any competitor. 50% stronger than traditional cam locks.

Innoclic Solution

Exceeds all regulatory requirements. 6 weeks faster than any competitor. 50% stronger than traditional cam locks.

Innoclic Solution

Exceeds all regulatory requirements. 6 weeks faster than any competitor. 50% stronger than traditional cam locks.

Innoclic Solution

Exceeds all regulatory requirements. 6 weeks faster than any competitor. 50% stronger than traditional cam locks.

Full ESG Compliance Guaranteed

Future Homes Standard 2026 requires 75% carbon reduction. Building Safety Act increasing compliance burden. ESG reporting mandatory for large developers.

Future Homes Standard 2026 requires 75% carbon reduction. Building Safety Act increasing compliance burden. ESG reporting mandatory for large developers.

Future Homes Standard 2026 requires 75% carbon reduction. Building Safety Act increasing compliance burden. ESG reporting mandatory for large developers.

Man assembling a round table, focused on the task with a smile. Furniture assembly and DIY concept.
Man assembling a round table, focused on the task with a smile. Furniture assembly and DIY concept.
Man assembling a round table, focused on the task with a smile. Furniture assembly and DIY concept.
Man assembling a round table, focused on the task with a smile. Furniture assembly and DIY concept.

Environmental

75% carbon footprint reduction

75% carbon footprint reduction

75% carbon footprint reduction

75% carbon footprint reduction

8x transport efficiency

8x transport efficiency

8x transport efficiency

8x transport efficiency

100% recyclable system

100% recyclable system

100% recyclable system

100% recyclable system

Zero installation waste

Zero installation waste

Zero installation waste

Zero installation waste

Circular economy ready

Circular economy ready

Circular economy ready

Circular economy ready

Man assembling a white table with brown legs. The man is wearing a blue jumpsuit and leaning over the furniture.
Man assembling a white table with brown legs. The man is wearing a blue jumpsuit and leaning over the furniture.
Man assembling a white table with brown legs. The man is wearing a blue jumpsuit and leaning over the furniture.
Man assembling a white table with brown legs. The man is wearing a blue jumpsuit and leaning over the furniture.

Social

Safer working conditions

Safer working conditions

Safer working conditions

Safer working conditions

Reduced site congestion

Reduced site congestion

Reduced site congestion

Reduced site congestion

Less community disruption

Less community disruption

Less community disruption

Less community disruption

Skills gap solution

Skills gap solution

Skills gap solution

Skills gap solution

Improved worker wellbeing

Improved worker wellbeing

Improved worker wellbeing

Improved worker wellbeing

Man fixing a wooden chair while wearing gloves. DIY furniture repair and restoration. Interior repair.
Man fixing a wooden chair while wearing gloves. DIY furniture repair and restoration. Interior repair.
Man fixing a wooden chair while wearing gloves. DIY furniture repair and restoration. Interior repair.
Man fixing a wooden chair while wearing gloves. DIY furniture repair and restoration. Interior repair.

Governance

Full supply chain transparency

Full supply chain transparency

Full supply chain transparency

Full supply chain transparency

BS 6222 certified

BS 6222 certified

BS 6222 certified

BS 6222 certified

Quality assurance guaranteed

Quality assurance guaranteed

Quality assurance guaranteed

Quality assurance guaranteed

Complete traceability

Complete traceability

Complete traceability

Complete traceability

Automated reporting

Automated reporting

Automated reporting

Automated reporting

Become a Certified
Innoclic Specialist

3-day intensive training unlocks premium earning potential

House Location - Realtor X Framer Template

BREEAM Outstanding 12+ Points

House Location - Realtor X Framer Template

BREEAM Outstanding 12+ Points

House Location - Realtor X Framer Template

BREEAM Outstanding 12+ Points

House Location - Realtor X Framer Template

BREEAM Outstanding 12+ Points

House Location - Realtor X Framer Template

LEED Platinum Ready

House Location - Realtor X Framer Template

LEED Platinum Ready

House Location - Realtor X Framer Template

LEED Platinum Ready

House Location - Realtor X Framer Template

LEED Platinum Ready

House Location - Realtor X Framer Template

BS 6222 Certified Strength

House Location - Realtor X Framer Template

BS 6222 Certified Strength

House Location - Realtor X Framer Template

BS 6222 Certified Strength

House Location - Realtor X Framer Template

BS 6222 Certified Strength

House Location - Realtor X Framer Template

EU Taxonomy Aligned Compliant

House Location - Realtor X Framer Template

EU Taxonomy Aligned Compliant

House Location - Realtor X Framer Template

EU Taxonomy Aligned Compliant

House Location - Realtor X Framer Template

EU Taxonomy Aligned Compliant

House Location - Realtor X Framer Template

ISO 14001 Environmental Standard

House Location - Realtor X Framer Template

ISO 14001 Environmental Standard

House Location - Realtor X Framer Template

ISO 14001 Environmental Standard

House Location - Realtor X Framer Template

ISO 14001 Environmental Standard

House Location - Realtor X Framer Template

Building Regs Part L Approved

House Location - Realtor X Framer Template

Building Regs Part L Approved

House Location - Realtor X Framer Template

Building Regs Part L Approved

House Location - Realtor X Framer Template

Building Regs Part L Approved

A carpenter wearing safety glasses screws parts of white cabinets together with a drill on a workbench.
A carpenter wearing safety glasses screws parts of white cabinets together with a drill on a workbench.
A carpenter wearing safety glasses screws parts of white cabinets together with a drill on a workbench.

With construction costs rising and ESG requirements tightening, Innoclic's January 2026 launch couldn't come at a better time. We're securing our Development Partner position now.

Projected Outcomes
• 6 weeks earlier completion
• £1.4m total savings
• Zero weather delays
• 94% fewer callbacks

Perfect for BTR Specifications

Perfect for BTR Specifications

Innoclic profiles coordinate seamlessly with your standard panel choices

Innoclic profiles coordinate seamlessly with your standard panel choices

Innoclic profiles coordinate seamlessly with your standard panel choices

Standard BTR Spec

White Innoclic profiles integrate perfectly with standard 18mm white MFC panels. Clean aesthetic for rental properties. Cost-effective without compromising quality.

Standard BTR Spec

White Innoclic profiles integrate perfectly with standard 18mm white MFC panels. Clean aesthetic for rental properties. Cost-effective without compromising quality.

Standard BTR Spec

White Innoclic profiles integrate perfectly with standard 18mm white MFC panels. Clean aesthetic for rental properties. Cost-effective without compromising quality.

Standard BTR Spec

White Innoclic profiles integrate perfectly with standard 18mm white MFC panels. Clean aesthetic for rental properties. Cost-effective without compromising quality.

Premium Units

Silver anodized profiles elevate oak veneer panels for penthouse specifications. Same system, premium finish. No additional installation complexity.

Premium Units

Silver anodized profiles elevate oak veneer panels for penthouse specifications. Same system, premium finish. No additional installation complexity.

Premium Units

Silver anodized profiles elevate oak veneer panels for penthouse specifications. Same system, premium finish. No additional installation complexity.

Premium Units

Silver anodized profiles elevate oak veneer panels for penthouse specifications. Same system, premium finish. No additional installation complexity.

ESG Materials

Natural aluminum profiles with recycled content panels meet sustainability targets. Full material transparency. Circular economy ready.

ESG Materials

Natural aluminum profiles with recycled content panels meet sustainability targets. Full material transparency. Circular economy ready.

ESG Materials

Natural aluminum profiles with recycled content panels meet sustainability targets. Full material transparency. Circular economy ready.

ESG Materials

Natural aluminum profiles with recycled content panels meet sustainability targets. Full material transparency. Circular economy ready.

6-Week Earlier Completion

Three simple steps to transform your development programme

Learn

01

See How It Works

Schedule a consultation to see Innoclic in action. We'll demonstrate the system and calculate specific timeline savings for your project. Visit our London showroom or arrange on-site demonstration.

See How It Works

Schedule a consultation to see Innoclic in action. We'll demonstrate the system and calculate specific timeline savings for your project. Visit our London showroom or arrange on-site demonstration.

Learn

01

See How It Works

Schedule a consultation to see Innoclic in action. We'll demonstrate the system and calculate specific timeline savings for your project. Visit our London showroom or arrange on-site demonstration.

Learn

01

See How It Works

Schedule a consultation to see Innoclic in action. We'll demonstrate the system and calculate specific timeline savings for your project. Visit our London showroom or arrange on-site demonstration.

Evaluate

02

Calculate Your ROI

Receive detailed project analysis. Review case studies from similar developments. Meet certified installers. Verify ESG compliance benefits.

Receive detailed project analysis. Review case studies from similar developments. Meet certified installers. Verify ESG compliance benefits.

Evaluate

02

Calculate Your ROI

Receive detailed project analysis. Review case studies from similar developments. Meet certified installers. Verify ESG compliance benefits.

Evaluate

02

Calculate Your ROI

Receive detailed project analysis. Review case studies from similar developments. Meet certified installers. Verify ESG compliance benefits.

Engage

03

Transform Your Business

Secure your Development Partner position. Lock in 2026 pricing. Schedule your first Innoclic project. Join industry leaders already committed.

Secure your Development Partner position. Lock in 2026 pricing. Schedule your first Innoclic project. Join industry leaders already committed.

Engage

03

Transform Your Business

Secure your Development Partner position. Lock in 2026 pricing. Schedule your first Innoclic project. Join industry leaders already committed.

Engage

03

Transform Your Business

Secure your Development Partner position. Lock in 2026 pricing. Schedule your first Innoclic project. Join industry leaders already committed.

Development Partner Program

Development Partner Program

Join leading UK developers securing competitive advantage through early access to revolutionary assembly technology. January 2026 market launch.

Join leading UK developers securing competitive advantage through early access to revolutionary assembly technology. January 2026 market launch.

Join leading UK developers securing competitive advantage through early access to revolutionary assembly technology. January 2026 market launch.

Colorful array of various colored rectangular shelf supports, including red, orange, and blue.
Colorful array of various colored rectangular shelf supports, including red, orange, and blue.
Colorful array of various colored rectangular shelf supports, including red, orange, and blue.
Colorful array of various colored rectangular shelf supports, including red, orange, and blue.

Gold Partner Status

12 Positions Remaining

12 Positions Remaining

12 Positions Remaining

12 Positions Remaining

Exclusive territory rights

Exclusive territory rights

Exclusive territory rights

Exclusive territory rights

Priority supply allocation

Priority supply allocation

Priority supply allocation

Priority supply allocation

Co-development input

Co-development input

Co-development input

Co-development input

Assembled kitchen cabinet being installed, with open doors. Close-up on the installation process.
Assembled kitchen cabinet being installed, with open doors. Close-up on the installation process.
Assembled kitchen cabinet being installed, with open doors. Close-up on the installation process.
Assembled kitchen cabinet being installed, with open doors. Close-up on the installation process.

Partner Requirements

500+ units annually

500+ units annually

500+ units annually

500+ units annually

ESG commitment demonstrated

ESG commitment demonstrated

ESG commitment demonstrated

ESG commitment demonstrated

Q3 2025 project ready

Q3 2025 project ready

Q3 2025 project ready

Q3 2025 project ready

Innovation mindset

Innovation mindset

Innovation mindset

Innovation mindset

Quality reputation

Quality reputation

Quality reputation

Quality reputation

Assembled kitchen cabinet being installed, with open doors. Close-up on the installation process.
Assembled kitchen cabinet being installed, with open doors. Close-up on the installation process.
Assembled kitchen cabinet being installed, with open doors. Close-up on the installation process.
Assembled kitchen cabinet being installed, with open doors. Close-up on the installation process.

Partner Benefits

6-week earlier completion

6-week earlier completion

6-week earlier completion

6-week earlier completion

Locked 2025 pricing

Locked 2025 pricing

Locked 2025 pricing

Locked 2025 pricing

Dedicated support team

Dedicated support team

Dedicated support team

Dedicated support team

Marketing collaboration

Marketing collaboration

Marketing collaboration

Marketing collaboration

Technology roadmap input

Technology roadmap input

Technology roadmap input

Technology roadmap input

Let's Transform Your Next Project

Every day of delay costs money. Start your 6-week advantage today.

Let's Transform Your Next Project

Every day of delay costs money. Start your 6-week advantage today.

Let's Transform Your Next Project

Every day of delay costs money. Start your 6-week advantage today.

Let's Transform Your Next Project

Every day of delay costs money. Start your 6-week advantage today.